System: Nassau Amelia Utility
Description: The Booster Pump Modification Project will replace the existing booster pump station located on the Omni property in Amelia Island. The new pump station will include a new 1-million-gallon ground storage tank, seven (7) split case pumps, a 500kW standby generator and associated electrical and controls equipment. The new ground storage tank has been constructed. The tapping the existing high and low service water supply lines have been completed. Construction of the underslab piping at the pump building has commenced. The project is anticipated to be substantially completion in April 2023.