Description:  The Booster Pump Modification Project will replace the existing booster pump station located on the Omni property in Amelia Island.  The new pump station will include a new 1-million-gallon ground storage tank, seven (7) split case pumps, a 500kW standby generator and associated electrical and controls equipment.  The temporary sidewalk required to redirect pedestrian traffic was constructed in February.  Demolition of the existing ground storage tank was completed by the end of February.  The underslab piping and encasements were installed and constructed in March.  The new ground storage tank construction will commence in April.  The project is anticipated to be substantially completion in April 2023.

Demolition of Existing Ground Storage Tank
Figure 1: Demolition of Existing Ground Storage Tank