The Generator Replacement Project provided a new 500kW generator to replace the existing dilapidated generator at the Amelia Island WWTP  The County issued the construction notice to proceed to Cogburn Brothers, Inc. on June 16th.  The new generator has been set, tested and commissioned.  The new automatic transfer switch which calls on the generator to start and stop with the interruption and restoration of utility power has been installed and commissioned.  The project was completed on December 31, 2021.

System: Nassau Amelia Utility

Amelia Island Generator
Figure 1: New Automatic Transfer Switch