Description:  The Plantation Bay WTP’s lime softening process and equipment is at the end of their useful life and requires replacement.  The miscellaneous improvements project includes abandonment of the existing lime softening equipment and installation of new nanofiltration equipment.  The project also includes various miscellaneous items aimed to increase treatment reliability and to provide a more consistent and disinfection byproduct free drinking water to the customers in the FGUA Flagler system.  The pilot study for the nanofiltration facility was complete in February 2022.  The 30% design submittal was provided in June.  Design in anticipated to be completed in November 2022.  Construction of the new facilities is expected to commence spring 2023.