Project Title: Amelia Island WTP Booster Pump Modification Project
System: Nassau Amelia Utility
Description: The Booster Pump Modification Project will replace the existing booster pump station located on the Omni property in Amelia Island. The new pump station will include a new 1-million-gallon ground storage tank, seven (7) split case pumps, a 500kW standby generator and associated electrical and controls equipment. The County issued the construction notice to proceed to Sawcross, Inc. on August 25th. Since then, Sawcross has submitted building permits to the County and technical submittals to the design consultant, GAI Consultants, Inc. Substantial completion of the project is anticipated in February 2023.