Project Title: Amelia Island WWTP Generator Replacement Project
System: Nassau Amelia Utility
Description: The Generator Replacement Project will provide a new 500kW generator to replace the existing dilapidated generator at the Amelia Island WWTP The County issued the construction notice to proceed to Cogburn Brothers, Inc. on June 16th. Since then, the generator’s concrete base pad was placed on August 4th. Subsequently, the generator was set on the pad on August 11th. Ring Power was onsite performing load bank testing and preparing the generator to be placed into service on September 16th. The project’s remaining activities include installation of the new automatic transfer switch (ATS), removal of the old generator and placing the new generator into service.