System: Flagler
Description: The Plantation Bay WWTP treatment plant’s treatment process equipment is at the end of its useful life and requires replacement. The Phase II Improvements project will provide a new digester, aeration basin and clarifier as the primary biological treatment process. The project will provide Class I reliability and increase plant capacity. Also, revisions to the WWTP’s effluent disposal process has been added to the project. The design is being provided by US Waters. The revised 90% design submittal was provided in February 2022 and the project is anticipated to be released for bid in May2022. Construction is anticipated to have a one-year duration.
Location Map: